Follow-up
Cleaning up after the clean-up crew
by Lisa Birk
Last Thursday, about a dozen citizens and three representatives from the
Massachusetts Department of Environmental Protection (DEP) waited patiently on
wooden chairs in Middleborough's handsome town hall. They were there to meet a
new team of scientists hired to clean up one of the state's filthiest
hazardous-waste sites, Rockland Industries, Inc., on Plymouth Street in
Middleborough (see "Who's Watching the Fox?", News and Features, August 25).
The clean-up has been a long time coming -- residents have complained about the
site for 32 years. The team hired to clean the site predicts that it will take
about five years to complete the job.
In 1995, the DEP classed the site "Tier IA" -- a designation reserved for the
dirtiest sites whose clean-ups lagged the furthest behind schedule. Over the
years, studies have documented the presence of 41 contaminants at Rockland,
including high concentrations of probable carcinogens such as dichlorobenzene,
which in animal experiments has been linked to liver and kidney problems, birth
defects, and increased rates of cancer. The site has stagnated at Phase II of
the state's five-phase clean-up program for 13 years. In Phase II, scientists
identify and locate contaminants. The actual clean-up doesn't come until Phase
IV.
For the past five years, the Striar family, who own Rockland, retained
scientists from KEY Environmental Services, Inc., to clean the site. But
neighbors complained to the DEP about KEY's work: barrels of chemicals
disappeared, but the papers documenting their disposal were missing; birds were
feathering their nests with asbestos fibers. Nothing happened until March, when
DEP's southeast section chief, Gerard Martin, stumbled on a hazardous-waste
release that KEY hadn't reported for four months. Regulations stipulate that
scientists inform DEP within 72 hours.
In July, the Striars let KEY go and then hired a phalanx of consultants: a
lawyer from Nutter, McClennen & Fish, an environmental project manager from
De Maximis, Inc., and a second environmental company, Roux Associates, Inc.,
for on-site work. And last week, Middleborough residents finally got to meet
the new team.
Nancy Enos, whose property abuts the site, came seeking "peace of mind," as did
most of the others in attendance. They peppered the presenters with questions,
referring to formal studies as well as to their own observations of
still-discharging pipes. The presenters predicted they'd complete Phase II by
next September. That came as welcome news, but the residents still had
questions.
Tom Sylvia, who lives in nearby Lakeville but grew up in Middleborough, and who
works as a remediation engineer cleaning hazardous-waste sites for a living,
wanted to know how "substandard" work could buy the owners another year before
they have to pony up remediation money. Meanwhile, neighbors are exposed to
serious pollution. "It doesn't seem fair," said Sylvia.
"We've been requesting an audit [from DEP] for one year," said Russell Enos,
citing several violations -- including some that concerned missing documents.
DEP lawyer Kevin Kiernan noted that the department couldn't audit the site,
because it is already receiving DEP oversight, but he said that the agency
would review KEY's work and is considering disciplinary action.
Bruce Thompson of De Maximis summed up the new team's commitment: "We have to
find the end of the contamination. If it leads off site, we will chase it. If
it leads to private houses, we'll be the first people at your door." On a scale
of one to 10, Nancy Enos left the meeting with a peace of mind ranked at
"seven" as a result of the consultants' efforts. "The only reason they're not
an eight is they could be very well versed [in presentation]," she said. Her
husband agreed, "This company's pretty good." He had just one other thought:
"The state needs to be a little more aggressive."